Written by 8:09 AM

As-Built Schedule

« Back to Glossary Index« Back to Previous Page

Definition: A comprehensive record detailing the actual progress and completion dates of all project activities, reflecting the true sequence and duration of tasks as they occurred during construction.​

Key Components:

  • Actual Start and Finish Dates: Documents the real commencement and completion dates of each activity.​
  • Activity Durations: Captures the time taken to complete each task.​
  • Sequence of Activities: Records the order in which tasks were performed, including any deviations from the original plan.​

Use Cases/Industries:

  • Construction: Provides a historical record of the construction process for future reference and analysis.​
  • Project Management: Assists in evaluating project performance and identifying areas for improvement.​
  • Legal and Claims Analysis: Serves as evidence in disputes regarding delays or changes to the project scope.​

Advantages:

  • Accurate Historical Record: Offers a detailed account of the project’s execution, aiding in transparency and accountability.​
  • Performance Evaluation: Enables comparison between planned and actual progress, facilitating lessons learned for future projects.​
  • Dispute Resolution: Provides factual data to support claims or resolve disagreements related to project timelines.​

Challenges:

  • Data Accuracy: Requires meticulous documentation throughout the project to ensure reliability.​
  • Resource Intensive: Collecting and maintaining detailed records can be time-consuming and may require dedicated personnel.​

Related Terms:

  • Baseline Schedule: The original approved project timeline used as a benchmark for tracking progress.​
  • As-Planned Schedule: The initial project plan outlining intended start and finish dates for activities.​
  • Schedule Variance: The difference between planned and actual progress in a project schedule.​

Example: A construction company completes a building project and compiles an as-built schedule, documenting the actual dates and durations of all activities. This record is then used to assess performance, address any claims, and inform planning for future projects.

Visited 1 times, 1 visit(s) today
« Back to Previous Page« Back to Glossary Index
Close